Heho Copper Project (JOGMEC) Contract: July – August 2014 Commenced drilling operations in July 2014 for short term contract in Nong Bua, Thailand. Drilled 600m of core in 2 weeks with Hanjin 700 rig. Equipment Provided: 1 x Hanjin 7000 1 x Tracked Carrier
Contract: July – August 2014 Commenced drilling operations in July 2014 for short term contract in Nong Bua, Thailand. Drilled 600m of core in 2 weeks with Hanjin 700 rig. Equipment Provided: 1 x Hanjin 7000 1 x Tracked Carrier