Xekong Power Plant Limited (Laos)

Contract: December 2013 to Present
Commenced drilling operations with two Haniin 4000 core rigs and two Thor RC rigs in late 2013 , until June 2014 when phase 1 of drilling was completed. Recommenced after monsoon season in October 2014 with 6 x hanjin 4000 drill rigs, and n x Hanjin 7000 rig.
Averaged 1500 meters per rig per month in coal formation,
Equipment Provided:
  • 6 x Hanjin 4000
  • 2 x Thor RC Rigs
  • 7 x Tracked Carriers
Expat Site Manager
Expat Mechanic with onsite workshop setup by PSI